Construction Update 4-7 to 4-20

Work completed 4/7 through 4/13:
  • 2 to 3 crews on-site
  • Frost laws lifted on April 8
  • Bored 1,681 feet on Werkner Road between Wildflower Ridge and Waterloo Road (Werkner PON)
  • Installed 3 pedestals on Werkner Road
  • Worked on road crossings and tying in lines for completed borings
  • Residents who have still not signed up received door tags
  • 740 total sign-ups
Work to be completed 4/14 through 4/20:
  • 4 to 5 crews on-site
  • Bore on Wildflower Ridge and Waterloo Road (crossing Werkner Road)
  • Work on road crossings and tying in lines for completed borings back through Island Lake PON
  • Order tracer wire
  • Pick-up cabinet / vault and deliver to Township Hall
  • MEC at Lyndon Township Hall on April 17 for the Open House (10:00 am to 6:00 pm) and Education Session (6:00 pm to 7:00 pm) – In-Home Installation