Work completed 4/7 through 4/13:
- 2 to 3 crews on-site
- Frost laws lifted on April 8
- Bored 1,681 feet on Werkner Road between Wildflower Ridge and Waterloo Road (Werkner PON)
- Installed 3 pedestals on Werkner Road
- Worked on road crossings and tying in lines for completed borings
- Residents who have still not signed up received door tags
- 740 total sign-ups
Work to be completed 4/14 through 4/20:
- 4 to 5 crews on-site
- Bore on Wildflower Ridge and Waterloo Road (crossing Werkner Road)
- Work on road crossings and tying in lines for completed borings back through Island Lake PON
- Order tracer wire
- Pick-up cabinet / vault and deliver to Township Hall
- MEC at Lyndon Township Hall on April 17 for the Open House (10:00 am to 6:00 pm) and Education Session (6:00 pm to 7:00 pm) – In-Home Installation