Areas referenced below can be located on this map
Work completed 2/17 through 2/23:
- 3 crews on-site
- Bored 1,344 feet on Werkner Road (Werkner PON)
- Bored 188 feet on N Territorial (Island Lake PON)
- Bored 1,969 feet on N Territorial (Central Office PON)
- Note: No boring two days this week due to weather
- Started conversations with Stantec (B2B trail contractor) regarding the pedestrian tunnel that will be crossing the Lyndon Township fiber along M-52 near Green Lake
- 575 total sign-ups for Broadband
Work to be completed 2/24 through 3/2:
- 3 crews on-site
- Continue boring on Werkner Road and N Territorial Road