Construction Update 2-17 to 3-2

Areas referenced below can be located on this map

Work completed 2/17 through 2/23:
  • 3 crews on-site
  • Bored 1,344 feet on Werkner Road (Werkner PON)
  • Bored 188 feet on N Territorial (Island Lake PON)
  • Bored 1,969 feet on N Territorial (Central Office PON)
  • Note:  No boring two days this week due to weather
  • Started conversations with Stantec (B2B trail contractor) regarding the pedestrian tunnel that will be crossing the Lyndon Township fiber along M-52 near Green Lake
  • 575 total sign-ups for Broadband
Work to be completed 2/24 through 3/2:
  • 3 crews on-site
  • Continue boring on Werkner Road and N Territorial Road