This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township, If you are looking for information that you do not find here or would like to ask a question, please contact at: Oversight@lyndonbroadband.org.
Project Updates
Construction Update 5-26 to 6-8
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 5/26 through 6/1: 5 crews on-site (Tuesday through Friday) Bored 335 feet on Mester Road (Werkner PON) Bored 1,025 feet on Mester Road (Island Lake PON) Bored 1,235 feet on Lindley Road (Island Lake PON) Bored 1,806 feet on Roe Road […]
Broadband service activated at Township Hall
Fiber optic cable has been pulled to the township hall and the broadband service has been activated. Planning is currently underway to make WiFi available for public use at the township hall. Additionally, a number of residential beta testers have been identified in the Werkner zone. Drops to their homes have been started and all […]
“Cutting the Cord”
Want to learn how you can take advantage of fiber internet to stream your favorite shows and say goodbye to your cable/satellite company? Join us at our upcoming Cutting the Cord presentation, and we’ll introduce you to the world of online streaming. We’ll discuss what you need to get started, what some of the most […]
Construction Update 5-19 to 6-1
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 5/19 through 5/25: 4 to 5 crews on-site Bored 174 feet on Mester Road (Werkner PON) Bored 2,346 feet on Lindley Road (Werkner PON) Bored 1,628 feet on Boyce Road (Boyce PON) Bored 301 feet on Coopersfield Road (Boyce PON) Installed […]
Construction update 5-12 to 5-25
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 5/12 through 5/18: 4 to 6 crews on-site Bored 570 feet on Werkner Road (Werkner PON) Bored 990 feet on Mester Road (Werkner PON) Bored 542 feet on Waterloo Road (Werkner PON) Bored 2,108 feet on Boyce Road (Boyce PON) Installed […]
MEC – May Construction Update
There’s light at the end of the tunnel, literally, as we prepare to bring fiber internet to life at Lyndon Township Hall. In this week’s construction update, Township officials announced that the cabinet and vault were installed last week, and they anticipate that service will be active for next week’s open house. Your MEC Internet […]
Construction update 5-5 to 5-18
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 5/5 through 5/11: 4 crews on-site Bored 290 feet on Werkner Road (Werkner PON) Bored 812 feet on Mester Road (Werkner PON) Installed 15 pedestals in Werkner PON Completed boring along mainline connecting the southeast corner of Lyndon Township to Township […]
Please Read – Drop Installation Process – MISS DIG
The following information will help to better understand the home installation (Drop) process. MEC (Midwest Energy and Communication) will be doing this work. Pay particular attention to MISS DIG information. The word Drop, refers to the the process of bringing the fiber optic cable from the road and attaching it to your home. As a […]
Construction Update 4-21 to 5-4
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 4/21 through 5/4: 4 crews on-site Bored 724 feet (Central Office PON) and 3,108 feet (Werkner PON) on Waterloo Road Bored 1,000 feet (Central Office PON) and 584 feet (Island Lake PON) on N Territorial Road Bored 1,360 feet on Mester […]
Construction Update 4-14 to 4-27
Work completed 4/14 through 4/20: 4 to 5 crews on-site Bored 1,336 feet (Werkner PON) and 132 feet (Island Lake PON) on Werkner Road Bored 1,355 feet on Waterloo Road (Werkner PON) Bored 192 feet on Wildflower Ridge (Werkner PON) Bored 132 feet on N Territorial Road (Island Lake PON) Bored 66 feet on Island […]