Work completed 5/19 through 5/25:
- 4 to 5 crews on-site
- Bored 174 feet on Mester Road (Werkner PON)
- Bored 2,346 feet on Lindley Road (Werkner PON)
- Bored 1,628 feet on Boyce Road (Boyce PON)
- Bored 301 feet on Coopersfield Road (Boyce PON)
- Installed 4 pedestals in Boyce PON
- Completed pulling fiber along mainline connecting the southeast corner of Lyndon Township to Township Hall
- Lots of people attended the May 22 Open House / Education Session
Work to be completed 5/26 through 6/1:
- 4 to 5 crews on-site
- Bore on Lindley Road (Werkner PON)
- Bore on Boyce Road (Boyce PON)
- Bore on Roe Road (Central Office PON)
- Work to activate Lyndon Township Hall