Work completed 5/19 through 5/25:
  • 4 to 5 crews on-site
  • Bored 174 feet on Mester Road (Werkner PON)
  • Bored 2,346 feet on Lindley Road (Werkner PON)
  • Bored 1,628 feet on Boyce Road (Boyce PON)
  • Bored 301 feet on Coopersfield Road (Boyce PON)
  • Installed 4 pedestals in Boyce PON
  • Completed pulling fiber along mainline connecting the southeast corner of Lyndon Township to Township Hall
  • Lots of people attended the May 22 Open House / Education Session
Work to be completed 5/26 through 6/1:
  • 4 to 5 crews on-site
  • Bore on Lindley Road (Werkner PON)
  • Bore on Boyce Road (Boyce PON)
  • Bore on Roe Road (Central Office PON)
  • Work to activate Lyndon Township Hall