Construction Update 5-26 to 6-8

Areas referenced below can be located on this map
Work completed 5/26 through 6/1:
  • 5 crews on-site (Tuesday through Friday)
  • Bored 335 feet on Mester Road (Werkner PON)
  • Bored 1,025 feet on Mester Road (Island Lake PON)
  • Bored 1,235 feet on Lindley Road (Island Lake PON)
  • Bored 1,806 feet on Roe Road (Central Office PON)
  • Bored 1,735 feet on Coopersfield Road (Boyce PON)
  • Installed 1 pedestal in Boyce PON
  • Continued to pull fiber through the installed conduit – a total of 25,758 feet of fiber has been pulled
  • Completed drops at five homes on Werkner Road for upcoming beta testing
  • Lyndon Township Hall activated with broadband service
  • Received final easement for DNR permit
Work to be completed 6/2 through 6/8:
  • 6 to 7 crews on-site
  • Bore on Lindley Road (Island Lake PON)
  • Bore on Stofer Road (Island Lake PON)
  • Bore on Island Lake Drive (Island Lake PON)
  • Bore on Boyce Road (Boyce PON)
  • Bore on Cooper Ridge Drive / Waterloo Road Connector (Werkner PON)
  • Bore on Mester Road (Werkner PON)
  • Work on Wildflower Ridge (Werkner PON)
  • Bore on Roe Road (Central Office PON
  • Continue to pull fiber through installed conduit
  • Record DNR easement to finish last permit