Work completed 4/14 through 4/20:
- 4 to 5 crews on-site
- Bored 1,336 feet (Werkner PON) and 132 feet (Island Lake PON) on Werkner Road
- Bored 1,355 feet on Waterloo Road (Werkner PON)
- Bored 192 feet on Wildflower Ridge (Werkner PON)
- Bored 132 feet on N Territorial Road (Island Lake PON)
- Bored 66 feet on Island Lake Road (Island Lake PON)
- Restored and staked
- Ordered tracer wire
- Picked-up cabinet / vault and delivered to Township Hall
- MEC hosted over 70 people at the April 17 Open House and Education Session on In-Home Installation
- Delivered door tags to those who have not signed up yet
- Mailed 4th postcard
- 772 total sign-ups
Work to be completed 4/21 through 4/27:
- 4 to 5 crews on-site
- Bore on Waterloo Road (both east and west of Werkner Road)
- Bore on North Territorial
- Install cabinet and vault at Lyndon Township Hall