Construction Update 4-14 to 4-27

Work completed 4/14 through 4/20:
  • 4 to 5 crews on-site
  • Bored 1,336 feet (Werkner PON) and 132 feet (Island Lake PON) on Werkner Road
  • Bored 1,355 feet on Waterloo Road (Werkner PON)
  • Bored 192 feet on Wildflower Ridge (Werkner PON)
  • Bored 132 feet on N Territorial Road (Island Lake PON)
  • Bored 66 feet on Island Lake Road (Island Lake PON)
  • Restored and staked
  • Ordered tracer wire
  • Picked-up cabinet / vault and delivered to Township Hall
  • MEC hosted over 70 people at the April 17 Open House and Education Session on In-Home Installation
  • Delivered door tags to those who have not signed up yet
  • Mailed 4th postcard
  • 772 total sign-ups
Work to be completed 4/21 through 4/27:
  • 4 to 5 crews on-site
  • Bore on Waterloo Road (both east and west of Werkner Road)
  • Bore on North Territorial
  • Install cabinet and vault at Lyndon Township Hall
Posted in Updates.