Construction update 5-12 to 5-25

Areas referenced below can be located on this map
Work completed 5/12 through 5/18:
  • 4 to 6 crews on-site
  • Bored 570 feet on Werkner Road (Werkner PON)
  • Bored 990 feet on Mester Road (Werkner PON)
  • Bored 542 feet on Waterloo Road (Werkner PON)
  • Bored 2,108 feet on Boyce Road (Boyce PON)
  • Installed 1 pedestal in Werkner PON and 3 pedestals in Boyce PON
  • Began to pull fiber along mainline connecting the southeast corner of Lyndon Township to Township Hall
  • MEC placed Network Interface Device (NID) and other equipment at Township Hall for upcoming activation
  • Prepare for May 22 Open House / Education Session
  •  total signups of 821
Work to be completed 5/19 through 5/25:
  • 4 to 5 crews on-site
  • Bore on Mester Road and Lindley Road (Werkner PON)
  • Bore on Boyce Road and Boyce Drive (Boyce PON)
  • Continue to pull cable along this mainline connecting the southeast corner of Lyndon Township and Township Hall
  • Work to activate Lyndon Township Hall
  • Attend May 22 Open House / Learning Education Session
Posted in Uncategorized, Updates.