Construction update 5-5 to 5-18

Areas referenced below can be located on this map

Work completed 5/5 through 5/11:
  • 4 crews on-site
  • Bored 290 feet on Werkner Road (Werkner PON)
  • Bored 812 feet on Mester Road (Werkner PON)
  • Installed 15 pedestals in Werkner PON
  • Completed boring along mainline connecting the southeast corner of Lyndon Township to Township Hall
Work to be completed 5/12 through 5/18:
  • 4 to 5 crews on-site
  • Begin to pull cable along this mainline connecting the southeast corner of Lyndon Township and Township Hall
  • Bore on Waterloo Road, Boyce Road and Mester Road
  • MEC to place NID and other equipment at Township Hall for upcoming activation
  • Continue planning for May 22 Open House / Learning Education Session –Tips, Tricks and Helpful Hints After Your Service Is Installed.