Construction Update 4-21 to 5-4

Areas referenced below can be located on this map

Work completed 4/21 through 5/4:
  • 4 crews on-site
  • Bored 724 feet (Central Office PON) and 3,108 feet (Werkner PON) on Waterloo Road
  • Bored 1,000 feet (Central Office PON) and 584 feet (Island Lake PON) on N Territorial Road
  • Bored 1,360 feet on Mester Road
  • Bored 380 feet on Island Lake Road (Island Lake PON)
  • Installed cabinet and vault at Lyndon Township Hall
  • 820 total sign-ups