Construction Update 11-10 to 11-23
- 6 bore crews on-site plus one fiber pulling crew and one splicing crew. Note: Minimal work on 11/11 and 11/12 due to the snowy and hazardous conditions.
- Bored 4,037 feet on Waterloo Road (Sugarloaf PON)
- Bored 300 feet on N Territorial Road (Wild Goose PON)
- Installed 20 pedestals in Sugarloaf PON
- Pulled 6,548 feet of fiber in Long Lake PON
- Spliced fiber in Central Office and Boyce PONs
- 18 new drops this week (totals to-date: 197 total drops – 82 in Werkner PON, 55 in Island Lake PON and 60 in Central Office PON)
- Spliced 6 jobs (totals to-date: 132 spliced – 81 in Werkner PON, 50 in Island Lake PON and 1 in Central Office PON)
- 8 new home installations (totals to-date: 86 with broadband – 65 in Werkner PON, 20 in Island Lake PON, and 1 in Central Office PON (Township Hall))
- 6 – 8 bore crews on-site plus one fiber pull crew and one splicing crew
- Bore on North Territorial (Sugarloaf and Wild Goose PONs)
- Bore on Cedar Drive (Sugarloaf PON)
- Bore on Lingane Road (Long Lake PON)
- Bore on Hadley Road (Wild Goose PON)
- Bore on Wild Goose Lake Road (Wild Goose PON)
- Bore on Sugarloaf Lake Road (Guinan PON)
- Bore on Bartell Road (Bruin PON)
- Continue to pull fiber in Long Lake PON and splice fiber in Central Office PON
- Continue drop installations in Werkner, Island Lake and Central Office PONs and start drop installations in Boyce PON
- Continue home installations in Werkner and Island Lake PONs
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (82) complete
Home Installations 77% (65) complete
84 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 81% (55) complete
Home Installations 29% (20) complete
68 Subscribers
Central Office
Mainline Boring 98% complete
Mainline Fiber Installation 73% complete
Drop Installations 76% (60) complete
Home Installations 1% (1) complete
79 Subscribers
Boyce
Mainline Boring 99% complete
Mainline Fiber Installation 95% complete
123 Subscribers
Sugarloaf
Mainline Boring 89% complete
Mainline Fiber Installation 14% complete
114 Subscribers
Long Lake
Mainline Boring 96% complete
Mainline Fiber Installation 24% complete
80 Subscribers
Wild Goose
Mainline Boring 29% complete
Mainline Fiber Installation 21% complete
45 Subscribers
Construction Update 11-3 to 11-16
- 9 to 10 bore crews on-site plus one fiber pulling crew and one splicing crew
- Bored 385 feet on M-52 (Central Office PON)
- Bored 170 feet on Cooper Ridge Road (Werkner PON)
- Bored 579 feet on Gaddis Road (Sugarloaf PON)
- Bored 1,470 feet on M-52 (Long Lake PON)
- Bored 2,482 feet on Hadley Road (Wild Goose PON)
- Bored 2,660 feet on Goodband Road (Wild Goose PON)
- Bored 570 feet on North Lake Road (Wild Goose PON)
- Installed 3 pedestals in Wild Goose PON
- Pulled 200 feet of fiber in Werkner PON and 7,148 feet of fiber in Long Lake PON
- Spliced fiber in Central Office and Boyce PONs
- 16 new drops this week (totals to-date: 179 total drops – 80 in Werkner PON, 54 in Island Lake PON and 45 in Central Office PON)
- Spliced 15 jobs (totals to-date: 111 spliced – 80 in Werkner PON, 45 in Island Lake PON and 1 in Central Office PON)
- 14 new home installations (totals to-date: 78 with broadband – 63 in Werkner PON, 14 in Island Lake PON, and 1 in Central Office PON (Township Hall))
- 8 bore crews on-site plus one fiber pull crew and one splicing crew (Note: No work was completed on Monday or Tuesday due to the snowy and hazardous conditions.)
- Bore on M-52 (Central Office and Long Lake PONs)
- Bore on Cedar Drive (Sugarloaf PON)
- Bore on Hadley Road (Long Lake and Wild Goose PONs)
- Bore on Sugarloaf Lake Road (Guinan PON)
- Bore on Bartell Road (Bruin PON)
- Continue to pull and splice fiber in Central Office and Boyce PONs
- Continue drop installations in Werkner, Island Lake and Central Office PONs
- Continue home installations in Werkner and Island Lake PONs
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 95% (80) complete
Home Installations 75% (63) complete
84 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 72% (49) complete
Home Installations 21% (14) complete
68 Subscribers
Central Office
Mainline Boring 98% complete
Mainline Fiber Installation 68% complete
Drop Installations 57% (45) complete
Home Installations 1% (1) complete
79 Subscribers
Boyce
Mainline Boring 99% complete
Mainline Fiber Installation 95% complete
123 Subscribers
Sugarloaf
Mainline Boring 79% complete
Mainline Fiber Installation 14% complete
114 Subscribers
Long Lake
Mainline Boring 96% complete
Mainline Fiber Installation 3% complete
80 Subscribers
Wild Goose
Mainline Boring 28% complete
Mainline Fiber Installation 21% complete
45 Subscribers
Construction update 10-27 to 11-9
- 8 to 9 bore crews on-site plus one fiber pulling crew and one splicing crew
- Bored 370 feet on M-52 (Central Office PON)
- Bored 264 feet on Cassidy Road (Boyce PON)
- Bored 3,882 feet on Waterloo Road (Sugarloaf PON)
- Bored 3,928 feet on M-52 (Long Lake PON)
- Bored 226 feet on Clark Lake Road (Long Lake PON)
- Bored 322 feet on Oakdale Road (Long Lake PON)
- Bored 120 feet on Stonehill Road (Long Lake PON)
- Pulled 8,602 feet of fiber in Boyce PON
- Spliced fiber in Central Office and Boyce PONs
- 26 new drops this week (totals to-date: 163 total drops – 80 in Werkner PON, 49 in Island Lake PON and 34 in Central Office PON)
- Spliced 2 jobs (totals to-date: 111 spliced – 80 in Werkner PON, 30 in Island Lake PON and 1 in Central Office PON)
- 7 new home installations (totals to-date: 64 with broadband – 58 in Werkner PON, 5 in Island Lake PON, and 1 in Central Office PON (Township Hall))
- 9 to 10 bore crews on-site plus one fiber pull crew and one splicing crew
- Bore on M-52 (Central Office and Long Lake PONs)
- Bore on Waterloo Road (Sugarloaf PON)
- Bore on Gaddis Road (Sugarloaf PON)
- Bore on Roe Road (Sugarloaf PON)
- Bore on Cedar Drive (Sugarloaf PON)
- Bore on Goodband Road (Wild Goose PON)
- Bore on Hadley Road (Wild Goose PON)
- Bore on Guinan Road (Guinan PON)
- Continue to pull and splice fiber in Central Office and Boyce PONs
- Continue drop installations in Werkner and Island Lake PONs
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 95% (80) complete
Home Installations 69% (58) complete
84 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 72% (49) complete
Home Installations 7% (5) complete
68 Subscribers
Central Office
Mainline Boring 97% complete
Mainline Fiber Installation 68% complete
Drop Installations 43% (34) complete
Home Installations 1% (1) complete
79 Subscribers
Boyce
Mainline Boring 99% complete
Mainline Fiber Installation 95% complete
123 Subscribers
Sugarloaf
Mainline Boring 77% complete
Mainline Fiber Installation 14% complete
114 Subscribers
Long Lake
Mainline Boring 91% complete
80 Subscribers
Construction Update 10-20 to 11-2
- 8 bore crews on-site plus one fiber pulling crew and one splicing crew
- Bored 524 feet on M-52 (Central Office PON)
- Bored 20 feet on N Territorial Road (Central Office PON)
- Bored 307 feet on Beeman Road (Boyce PON)
- Bored 290 feet on Roe Road (Boyce PON)
- Bored 2,000 feet on Waterloo Road (Sugarloaf PON)
- Bored 3,752 feet on M-52 (Long Lake PON)
- Bored 1,555 feet on Clark Lake Road (Long Lake PON)
- Bored 1,457 feet on Waterloo Road (Long Lake PON)
- Bored 2,437 feet on Joslin Lake Road (Wild Goose PON)
- Installed 12 pedestals in Long Lake PON and 7 pedestals in Wild Goose PON
- Pulled 5,894 feet in Boyce PON and 5,694 feet in Sugarloaf PON
- Spliced fiber in Central Office and Boyce PONs
- 41 new drops this week (totals to-date: 137 total drops – 79 in Werkner PON, 45 in Island Lake PON and 13 in Central Office PON)
- Spliced 32 jobs (totals to-date: 109 spliced – 78 in Werkner PON, 30 in Island Lake PON and 1 in Central Office PON)
- 14 new home installations (totals to-date: 57 with broadband – 51 in Werkner PON, 5 in Island Lake PON, and 1 in Central Office PON (Township Hall))
- 8 bore crews on-site plus one fiber pull crew and one splicing crew. (With the rainy weather, there are a couple of non-work days this week.)
- Bore on M-52 (Central Office and Long Lake PONs)
- Bore on Beeman Road (Boyce PON)
- Bore on Waterloo Road (Sugarloaf PONs)
- Bore on Goodband Road (Wild Goose PON)
- Continue to pull and splice fiber in Central Office and Boyce PONs
- Continue drop installations in Werkner and Island Lake PONs
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 94% (79) complete
Home Installations 61% (51) complete
84 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 66% (45) complete
Home Installations 7% (5) complete
68 Subscribers
Central Office
Mainline Boring 97% complete
Mainline Fiber Installation 68% complete
79 Subscribers
Boyce
Mainline Boring 99% complete
Mainline Fiber Installation 76% complete
123 Subscribers
Sugarloaf
Mainline Boring 62% complete
114 Subscribers
Long Lake
Mainline Boring 86% complete
80 Subscribers
Zones and Map
The township has been divided into 11 zones or in networking terms, PONs (Passive Optical Networks), These zones represent the sequence in which construction and installations will occur. The layout of the 11 areas referenced below can be seen on this map:
LYNDON DESIGN 110518
- Werkner
- Island Lake
- Central Office
- Boyce
- Sugarloaf
- Guinan
- Long Lake
- Wild Goose
- Bruin
- Joslin
- Ellsworth
Construction Update 10-13 to 10-26
- 9 bore crews on-site plus one fiber pulling crew and one splicing crew
- Bored 1,063 feet on M-52 (Central Office PON)
- Bored 264 feet on Leeke Road (Boyce PON)
- Bored 1,479 feet on Roe Road (Boyce PON)
- Bored 600 feet on M-52 (Long Lake PON)
- Bored 946 feet on Waterloo Road (Long Lake PON)
- Bored 374 feet on Clark Lake Road (Long Lake PON)
- Bored 3,204 feet on Joslin Lake Road (Wild Goose PON)
- Bored 260 feet on N Territorial Road (Wild Goose PON)
- Installed 1 pedestal in Central Office PON, 4 pedestals in Boyce PON, 2 pedestals in Wild Goose PON and 4 pedestals in Ellsworth PON
- Pulled 1,160 feet of fiber in Central Office PON and 6,994 feet in Boyce PON
- Spliced fiber in Central Office and Boyce PONs
- 10 new drops this week (totals to-date: 96 total drops – 75 in Werkner PON, 20 in Island Lake PON and 1 in Central Office PON)
- Spliced 20 jobs (totals to-date: 77 spliced – 67 in Werkner PON, 9 in Island Lake PON and 1 in Central Office PON)
- 9 new home installations (totals to-date: 43 with broadband – 41 in Werkner PON, 1 in Island Lake PON, and 1 in Central Office PON (Township Hall))
- 8 bore crews on-site plus one fiber pull crew and one splicing crew
- Bore on M-52 (Central Office and Long Lake PONs)
- Bore on Boyce Road Road (Boyce PON)
- Bore on Clark Lake Road (Long Lake PON)
- Bore on Waterloo Road (Sugarloaf and Long Lake PONs)
- Bore on Joslin Lake Road (Wild Goose PON)
- Continue to pull and splice fiber in Central Office and Boyce PONs
- Continue drop installations in Werkner and Island Lake PONs. Update: 42 drops completed this week!
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 89% (75) complete
Home Installations 49% (41) complete
84 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 29% (20) complete
Home Installations underway
68 Subscribers
Central Office
Mainline Boring 96% complete
Mainline Fiber Installation 68% complete
79 Subscribers
Boyce
Mainline Boring 99% complete
Mainline Fiber Installation 63% complete
123 Subscribers
Sugarloaf
Mainline Boring 62% complete
114 Subscribers
Long Lake
Mainline Boring 66% complete
80 Subscribers
Drop Information
Drop is the term used to describe the process of bringing the fiber optic cable from the main line fiber at the road and connecting it to an enclosure on your residence.
Here is information about the process and sequence of events that will occur.
- MEC’s Underground Contractor (drop installer) will call in a request to Miss Dig. You do not need to call MISS DIG for this.
Miss Dig will locate all public underground facilities and you will see flags on your property marking their location. - When you see these flags , it is a good time to mark / identify any of your
personal underground facilities, including but not limited to: sprinkler systems, propane lines, septic lines, water lines, invisible pet fence, etc. You can use Cones, spray paint, flags, etc.
MEC does not contact people before beginning drop work on their property, unless you requested that during the sign up process.
3. MEC’s Underground Contractor will bury a fiber optic cable from the main line to your home
4. A housebox (enclosure) will be placed on the outside of your home. This will be where the fiber will enter your home. This can be where all other utilities are located, where your current internet/telephone service enters your home, or just the best location to reach the desired end point. This something you specified during the sign up process.
5. After the drop is complete, there are two steps in the home installation. A Splicing crew is assigned to splice fiber inside the pedestal and housebox/enclosure. This process connects your drop fiber to the main line fiber and adds the fiber cable that will be run into your home. You do not need to be present during this process.
Once the splicing is complete, you will receive a call from MEC to schedule a time for home installation.
Home installs may be either a self install or installation by a technician. In terms of scheduling, one does not happen sooner than the other. In a self install situation.a technician is still present. They bring the necessary electronics for the install and they remain on site (outside of the home) for up to 1.5 hours to ensure the connection is activated. The difference between a self install and a regular in home installation by a technician is that they do not enter your home. If you have concerns about COVID -19 and are not comfortable with the safety protocols outlined in May MEC update, we will support you through a self-installation process.
- Do you have a 5/8-16” drill bit (stick-built house)?
- Do you have a 5/8-16” masonry bit with a hammer drill (brick, cement or anything not stick built)?
- Are you comfortable drilling a hole through your home?
- Are you comfortable installing screw clips to secure the fiber?
- Talk through placement of Modem and determine how much cable is needed.
Construction Update 10-6 to 10-19
- 9 bore crews on-site plus one fiber pulling crew and one splicing crew
- Bored 1,534 feet on M-52 (Central Office PON)
- Bored 911 feet on Leeke Road (Boyce PON)
- Bored 773 feet on Cassidy Road (Boyce PON)
- Bored 530 feet on Roe Road (Boyce PON)
- Bored 1,610 feet on Osius Road (Sugarloaf PON)
- Bored 692 feet on Beeman Road (Sugarloaf PON)
- Bored 2,058 feet on Waterloo Road (Long Lake PON)
- Bored 736 feet on Clark Lake Road (Long Lake PON)
- Bored 248 feet on Oakdale Drive (Long Lake PON)
- Installed 2 pedestals in Central Office PON and 4 pedestals in Long Lake PON
- Pulled 2,582 feet of fiber in Central Office PON, 7,618 feet in Boyce PON and 1,040 feet in Long Lake PON
- Spliced fiber in Central Office and Boyce PONs
- No new sign-ups
- 13 new drops this week (totals to-date: 86 total drops – 67 in Werkner PON, 18 in Island Lake PON and 1 in Central Office PON (Township Hall))
- Spliced 1 job
- 11 new home installations (totals to-date: 34 with broadband – 32 in Werkner PON, 1 in Island Lake PON, and 1 in Central Office PON)
- 9 bore crews on-site plus one fiber pull crew and one splicing crew
- Bore on M-52 (Central Office PON)
- Bore on Roe Road (Boyce PON)
- Bore on Clark Lake Road (Long Lake PON)
- Bore on Waterloo Road (Sugarloaf and Long Lake PONs)
- Bore on Joslin Lake Road (Wild Goose PON)
- Continue to pull and splice fiber in Central Office and Boyce PONs
- Continue drop installations in Werkner and Island Lake PONs
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 80% (67) complete
Home Installations 38% (32) complete
84 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drops Installations 26% (18) complete
Home Installations underway
68 Subscribers
Central Office
Mainline Boring 93% complete
Mainline Fiber Installation 66% complete
79 Subscribers
Boyce
Mainline Boring 99% complete
Mainline Fiber Installation 48% complete
123 Subscribers
Sugarloaf
Mainline Boring 62% complete
114 Subscribers
Construction Update 9-25 to 10-12
- 8 to 9 bore crews on-site plus one fiber pulling crew and one splicing crew
- Bored 774 feet on M-52 (Central Office PON)
- Bored 800 feet on North Territorial Road (Central Office PON)
- Bored 1,158 feet on Roepke Court (Ellsworth PON)
- Bored 1,940 feet on Waterloo Road (Sugarloaf PON)
- Bored 198 feet on Lingane Road (Long Lake PON)
- Bored 566 feet on Westbourne Court (Long Lake PON)
- Bored 1,377 feet on Waterloo Road (Long Lake PON)
- Installed 1 pedestal in Boyce PON and 2 pedestals in Sugarloaf PON
- Pulled 2,654 feet of fiber in Boyce PON
- Spliced fiber in Central Office and Boyce PONs
- No new sign-ups
- No new drops this week (totals to-date: 74 total drops – 55 in Werkner PON, 18 in Island Lake PON and 1 in Central Office PON (Township Hall))
- Spliced 8 jobs
- 4 new home installations (totals to-date: 22 with broadband – 20 in Werkner PON, 1 in Island Lake PON, and 1 in Central Office PON)
- 9 bore crews on-site plus one fiber pull crew and one splicing crew
- Bore on M-52 (Central Office and Boyce PON)
- Bore on Leeke Road (Boyce PON)
- Bore on Roe Road (Boyce PON)
- Bore on Westbourne Court (Long Lake PON)
- Bore on Oakdale Court (Long Lake PON)
- Bore on Clark Lake Road (Long Lake PON)
- Bore on Waterloo Road (Sugarloaf and Long Lake PONs)
- Bore on Osius Road (Sugarloaf PON)
- Continue to pull and splice fiber in Central Office and Boyce PONs
- Continue drop installations in Werkner and Island Lake PONs
There are four basic phases of work in bringing internet service to your home:
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 65% complete
Home Installations 24% complete
84 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drops Installations underway
Home Installations underway
68 Subscribers
Central Office
Mainline Boring 90% complete
Mainline Fiber Installation 61% complete
79 Subscribers
Boyce
Mainline Boring 95% complete
Mainline Fiber Installation 32% complete
123 Subscribers
Sugarloaf
Mainline Boring 57% complete
114 Subscribers