Construction Update 10-11 to 10-24

Areas referenced below can be located on this map
Work completed 10/11/2020 through 10/17/2020:
  • Completed mainline splicing in Ellsworth PON
  • Installed 36 home drops in Werkner, Island Lake, Sugarloaf, Joslin and Ellsworth PONs (totals to date: 895 drops – 97 in Werkner PON, 75 in Island Lake PON, 87 in Central Office PON, 131 in Boyce PON, 124 in Sugarloaf PON, 43 in Guinan PON, 84 in Long Lake PON, 52 in Wild Goose PON, 55 in Bruin PON, 75 in Joslin PON and 72 in Ellsworth PON).
  • Began splicing home drops in Ellsworth PON
  • Spliced 41 home drops in Werkner, Island Lake, Sugarloaf, Long Lake, Wild Goose, Joslin and Ellsworth PONs (totals to date: 795 spliced – 96 in Werkner PON, 73 in Island Lake PON, 87 in Central Office PON, 130 in Boyce PON, 119 in Sugarloaf PON, 42 in Guinan PON, 84 in Long Lake PON, 51 in Wild Goose PON, 55 in Bruin PON, 57 in Joslin PON and 1 in Ellsworth PON).
  • Completed 38 new home installations in Sugarloaf, Long Lake, Wild Goose, Bruin and Joslin PONs (totals to date: 734 with broadband – 94 in Werkner PON, 72 in Island Lake PON, 85 in Central Office PON, 126 in Boyce PON, 115 in Sugarloaf PON, 39 in Guinan PON, 82 in Long Lake PON, 44 in Wild Goose PON, 51 in Bruin PON and 26 in Joslin PON).
Work to be completed 10/18/2020 through 10/24/2020:
  • Continue to install home drops in Ellsworth PON
  • Continue home drop splicing in Sugarloaf, Joslin and Ellsworth PONs
  • Begin home installations in Ellsworth PON
  • Continue home installations in Central Office, Boyce, Sugarloaf, Guinan, Long Lake, Wild Goose, Bruin and Joslin PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (97) complete
Home Installations 97% (94) complete
97 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (75) complete
Home Installations 96% (72) complete
75 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 96% (85) complete
89 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (131) complete
Home Installations 95% (126) complete
132 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (124) complete
Home Installations 93% (115) complete
124 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 91% (39) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (84) complete
Home Installations 98% (82) complete
84 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (53) complete
Home Installations 83% (44) complete
53 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (55) complete
Home Installations 91% (51) complete
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (75) complete
Home Installations 35% (26) complete
75 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 79% (72) complete
Home Installations begin late October
91 Subscribers

Construction Update 10-4 to 10-17

Areas referenced below can be located on this map
Work completed 10/4/2020 through 10/10/2020:
  • Installed 22 home drops in Bruin, Joslin and Ellsworth PONs (totals to date: 859 drops – 95 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 131 in Boyce PON, 121 in Sugarloaf PON, 43 in Guinan PON, 84 in Long Lake PON, 52 in Wild Goose PON, 55 in Bruin PON, 70 in Joslin PON and 49 in Ellsworth PON).
  • Began splicing home drops in Joslin PON
  • Spliced 26 home drops in Werkner, Bruin and Joslin PONs (totals to date: 754 spliced – 95 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 130 in Boyce PON, 118 in Sugarloaf PON, 42 in Guinan PON, 83 in Long Lake PON, 49 in Wild Goose PON, 55 in Bruin PON and 23 in Joslin PON).
  • Completed 21 new home installations in Werkner, Sugarloaf, Bruin and Joslin PONs (totals to date: 696 with broadband – 94 in Werkner PON, 72 in Island Lake PON, 85 in Central Office PON, 126 in Boyce PON, 113 in Sugarloaf PON, 39 in Guinan PON, 81 in Long Lake PON, 40 in Wild Goose PON, 42 in Bruin PON and 4 in Joslin PON).
Work to be completed 10/11/2020 through 10/17/2020:
  • Complete mainline splicing in Ellsworth PON
  • Continue to install home drops in Joslin and Ellsworth PONs
  • Continue home drop splicing in Sugarloaf, Wild Goose, and Joslin PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf, Guinan, Long Lake, Wild Goose, Bruin and Joslin PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (95) complete
Home Installations 99% (94) complete
95 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (72) complete
Home Installations 100% (72) complete
72 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 96% (85) complete
89 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (131) complete
Home Installations 95% (126) complete
132 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (121) complete
Home Installations 93% (113) complete
121 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 91% (39) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (84) complete
Home Installations 96% (81) complete
84 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (52) complete
Home Installations 75% (40) complete
53 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 96% (55) complete
Home Installations 74% (42) complete
57 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (70) complete
Home Installations 6% (4) complete
70 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 54% (49) complete
Home Installations begin late October
91 Subscribers

Construction Update 9-27 to 10-10

Areas referenced below can be located on this map
Work completed 9/27/2020 through 10/3/2020:
  • Begin testing in Ellsworth PON
  • Installed 17 home drops in Werkner, Long Lake, Bruin and Joslin PONs (totals to date: 837 drops – 95 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 131 in Boyce PON, 121 in Sugarloaf PON, 43 in Guinan PON, 84 in Long Lake PON, 52 in Wild Goose PON, 53 in Bruin PON, 51 in Joslin PON and 48 in Ellsworth PON).
  • Spliced 12 home drops in Sugarloaf, Wild Goose and Bruin PONs (totals to date: 728 spliced – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 130 in Boyce PON, 118 in Sugarloaf PON, 42 in Guinan PON, 83 in Long Lake PON, 49 in Wild Goose PON and 53 in Bruin PON).
  • Completed 19 new home installations in Boyce, Sugarloaf, Wild Goose, and Bruin PONs (totals to date: 675 with broadband – 93 in Werkner PON, 72 in Island Lake PON, 85 in Central Office PON, 126 in Boyce PON, 111 in Sugarloaf PON, 39 in Guinan PON, 81 in Long Lake PON, 40 in Wild Goose PON and 28 in Bruin PON).
Work to be completed 10/4/2020 through 10/10/2020:
  • Finish testing Ellsworth PON
  • Begin splicing home drops in Joslin PON
  • Continue to install home drops in Bruin, Joslin and Ellsworth PONs
  • Continue home drop splicing in Sugarloaf, Wild Goose, and Bruin PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf, Guinan, Long Lake, Wild Goose, and Bruin PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (95) complete
Home Installations 98% (93) complete
95 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (72) complete
Home Installations 100% (72) complete
72 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 96% (85) complete
89 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (131) complete
Home Installations 95% (126) complete
132 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (121) complete
Home Installations 92% (111) complete
121 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 91% (39) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (84) complete
Home Installations 96% (81) complete
84 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (52) complete
Home Installations 75% (40) complete
53 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 95% (53) complete
Home Installations 50% (28) complete
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 78% (51) complete
Home Installations begin mid-October
65 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 53% (48) complete
Home Installations begin late October
91 Subscribers

Construction update 9-20 to 10-3

Areas referenced below can be located on this map

Work completed 9/20/2020 through 9/26/2020:
  • Completed splicing in Ellsworth PON
  • Lit Joslin and Ellsworth PONs last Friday
  • Installed 25 home drops in Joslin and Ellsworth PONs (totals to date: 820 drops – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 131 in Boyce PON, 121 in Sugarloaf PON, 43 in Guinan PON, 83 in Long Lake PON, 52 in Wild Goose PON, 47 in Bruin PON, 42 in Joslin PON and 48 in Ellsworth PON).
  • Spliced 0 home drops in Long Lake and Bruin PONs (totals to date: 716 spliced – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 130 in Boyce PON, 115 in Sugarloaf PON, 42 in Guinan PON, 83 in Long Lake PON, 48 in Wild Goose PON and 45 in Bruin PON).
  • Completed 16 new home installations in Long Lake, Wild Goose, and Bruin PONs (totals to date: 656 with broadband – 93 in Werkner PON, 72 in Island Lake PON, 85 in Central Office PON, 125 in Boyce PON, 110 in Sugarloaf PON, 39 in Guinan PON, 81 in Long Lake PON, 38 in Wild Goose PON and 13 in Bruin PON).
Work to be completed 9/27/2020 through 10/3/2020:
  • Finish remaining equipment installation in Ellsworth PON
  • Continue to install home drops in Bruin, Joslin and Ellsworth PONs
  • Continue home drop splicing in Sugarloaf, Wild Goose, and Bruin PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf, Guinan, Long Lake, Wild Goose, and Bruin PONs
  • Begin home splicing and installations in Joslin PON
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (94) complete
Home Installations 99% (93) complete
94 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (72) complete
Home Installations 100% (72) complete
72 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 96% (85) complete
89 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (131) complete
Home Installations 95% (125) complete
132 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (121) complete
Home Installations 91% (110) complete
121 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 91% (39) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (83) complete
Home Installations 98% (81) complete
83 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (52) complete
Home Installations 72% (38) complete
53 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 84% (47) complete
Home Installations 23% (13) complete
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 65% (42) complete
Home Installations begin early October
65 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 53% (48) complete
Home Installations begin mid-October
91 Subscribers

Attachments area

Construction Update 9-13 to 9-26

Areas referenced below can be located on this map
Work completed 9/13/2020 through 9/19/2020:
  • Continued splicing in Ellsworth PON
  • Installed 35 home drops in Joslin and Ellsworth PONs (totals to date: 795 drops – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 131 in Boyce PON, 121 in Sugarloaf PON, 43 in Guinan PON, 83 in Long Lake PON, 52 in Wild Goose PON, 45 in Bruin PON, 19 in Joslin PON and 48 in Ellsworth PON).
  • Spliced 19 home drops in Long Lake and Bruin PONs (totals to date: 715 spliced – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 130 in Boyce PON, 115 in Sugarloaf PON, 42 in Guinan PON, 83 in Long Lake PON, 47 in Wild Goose PON and 45 in Bruin PON).
  • Completed 12 new home installations in Werkner, Island Lake, Central Office, Sugarloaf, Boyce, Long Lake, Wild Goose, and Bruin PONs (totals to date: 640 with broadband – 93 in Werkner PON, 72 in Island Lake PON, 85 in Central Office PON, 125 in Boyce PON, 110 in Sugarloaf PON, 39 in Guinan PON, 80 in Long Lake PON, 35 in Wild Goose PON and 1 in Bruin PON).
Work to be completed 9/20/2020 through 9/26/2020:
  • Continue splicing in Ellsworth PON
  • Continue to install home drops in Bruin, Joslin and Ellsworth PONs
  • Continue home drop splicing in Sugarloaf, Wild Goose, and Bruin PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf, Guinan, Long Lake, Wild Goose, and Bruin PONs
  • Begin home installations in Joslin PON
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (94) complete
Home Installations 99% (93) complete
94 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (72) complete
Home Installations 100% (72) complete
72 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 96% (85) complete
89 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (131) complete
Home Installations 95% (125) complete
132 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (121) complete
Home Installations 91% (110) complete
121 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 91% (39) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (83) complete
Home Installations 96% (80) complete
83 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (52) complete
Home Installations 66% (35) complete
53 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 80% (45) complete
Home Installations 2% (1) complete
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 29% (19) complete
Home Installations begin early October
65 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 53% (48) complete
Home Installations begin mid-October
91 Subscribers

Attachments area

Construction Update 9-6 to 9-19

Areas referenced below can be located on this map
Work completed 9/6/2020 through 9/12/2020:
  • Begin splicing in Ellsworth PON
  • Installed 11 home drops in Wild Goose and Ellsworth PONs (totals to date: 760 drops – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 131 in Boyce PON, 121 in Sugarloaf PON, 43 in Guinan PON, 83 in Long Lake PON, 52 in Wild Goose PON, 45 in Bruin PON, 1 in Joslin PON and 31 in Ellsworth PON).
  • Spliced 22 home drops in Boyce, Sugarloaf, and Bruin PONs (totals to date: 696 spliced – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 130 in Boyce PON, 115 in Sugarloaf PON, 42 in Guinan PON, 82 in Long Lake PON, 47 in Wild Goose PON and 27 in Bruin PON).
  • Completed 14 new home installations in Island Lake, Boyce, Sugarloaf, Long Lake, and Wild Goose PONs (totals to date: 628 with broadband – 92 in Werkner PON, 71 in Island Lake PON, 84 in Central Office PON, 124 in Boyce PON, 107 in Sugarloaf PON, 39 in Guinan PON, 79 in Long Lake PON, and 32 in Wild Goose PON).
Work to be completed 9/13/2020 through 9/19/2020:
  • Continue splicing in Ellsworth PON
  • Continue to install home drops in Bruin, Joslin and Ellsworth PONs
  • Continue home drop splicing in Sugarloaf, Wild Goose, and Bruin PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf, Guinan, Long Lake and Wild Goose PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (94) complete
Home Installations 98% (92) complete
94 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (72) complete
Home Installations 99% (71) complete
72 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 94% (84) complete
89 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (131) complete
Home Installations 94% (124) complete
132 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (121) complete
Home Installations 88% (107) complete
121 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 91% (39) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (83) complete
Home Installations 95% (79) complete
83 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (52) complete
Home Installations 60% (32) complete
53 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 80% (45) complete
Home Installations begin late September
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 2% (1) complete
Home Installations begin early October
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 34% (31) complete
Home Installations begin mid-October
91 Subscribers

Construction Update 8-30 to 9-12

Areas referenced below can be located on this map

Work completed 8/30/2020 through 9/5/2020:
  • Completed splicing in Joslin PON
  • Installed 28 home drops in Bruin, Joslin and Ellsworth PONs (totals to date: 747 drops – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 131 in Boyce PON, 121 in Sugarloaf PON, 43 in Guinan PON, 83 in Long Lake PON, 51 in Wild Goose PON, 43 in Bruin PON, 1 in Joslin PON and 21 in Ellsworth PON).
  • Spliced 15 home drops in Werkner, Island Lake, Sugarloaf, Wild Goose and Bruin PONs (totals to date: 674 spliced – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 129 in Boyce PON, 114 in Sugarloaf PON, 42 in Guinan PON, 82 in Long Lake PON, 47 in Wild Goose PON and 7 in Bruin PON).
  • Completed 26 new home installations in Island Lake, Sugarloaf, Long Lake, and Wild Goose PONs (totals to date: 614 with broadband – 92 in Werkner PON, 70 in Island Lake PON, 84 in Central Office PON, 123 in Boyce PON, 105 in Sugarloaf PON, 39 in Guinan PON, 76 in Long Lake PON, and 25 in Wild Goose PON).
Work to be completed 9/6/2020 through 9/12/2020:
  • Begin splicing in Ellsworth PON
  • Continue to install home drops in Bruin, Joslin and Ellsworth PONs
  • Continue home drop splicing in Sugarloaf, Wild Goose, and Bruin PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf, Guinan, Long Lake and Wild Goose PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (94) complete
Home Installations 98% (92) complete
94 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (72) complete
Home Installations 97% (70) complete
72 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 94% (84) complete
89 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (131) complete
Home Installations 93% (123) complete
132 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (121) complete
Home Installations 87% (105) complete
121 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 91% (39) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (83) complete
Home Installations 92% (76) complete
83 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (51) complete
Home Installations 48% (25) complete
52 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 77% (43) complete
Home Installations begin late September
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 2% (1) complete
Home Installations begin early October
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 23% (21) complete
Home Installations begin mid-October
91 Subscribers

Construction Update 8-23 to 9-5

Areas referenced below can be located on this map

Work completed 8/23/2020 through 8/29/2020:
  • Continued splicing in Joslin PON
  • Lit Bruin PON splitter cabinet
  • Installed 27 home drops in Werkner, Island Lake, Boyce, Sugarloaf, and Bruin PONs (totals to date: 719 drops – 94 in Werkner PON, 72 in Island Lake PON, 87 in Central Office PON, 131 in Boyce PON, 121 in Sugarloaf PON, 43 in Guinan PON, 83 in Long Lake PON, 51 in Wild Goose PON and 37 in Bruin PON).
  • Spliced 12 home drops in Island Lake, Boyce, Sugarloaf, Long Lake, and Wild Goose PONs (totals to date: 659 spliced – 93 in Werkner PON, 69 in Island Lake PON, 87 in Central Office PON, 129 in Boyce PON, 113 in Sugarloaf PON, 42 in Guinan PON, 82 in Long Lake PON, and 44 in Wild Goose PON).
  • Completed 17 new home installations in Island Lake, Boyce, Guinan, Long Lake and Wild Goose PONs (totals to date: 588 with broadband – 92 in Werkner PON, 68 in Island Lake PON, 84 in Central Office PON, 123 in Boyce PON, 103 in Sugarloaf PON, 39 in Guinan PON, 68 in Long Lake PON, and 11 in Wild Goose PON).
Work to be completed 8/30/2020 through 9/5/2020:
  • Continue splicing in Joslin PON
  • Continue to install home drops in Bruin PON
  • Continue home drop splicing in Sugarloaf and Wild Goose PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf,  Guinan, Long Lake and Wild Goose PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (94) complete
Home Installations 98% (92) complete
94 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (72) complete
Home Installations 94% (68) complete
72 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 94% (84) complete
89 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (131) complete
Home Installations 93% (123) complete
132 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (121) complete
Home Installations 85% (103) complete
121 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 91% (39) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (83) complete
Home Installations 82% (68) complete
83 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (51) complete
Home Installations 21% (11) complete
52 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 66% (37) complete
Home Installations begin late September
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-September
Home Installations begin early October
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin late September
Home Installations begin mid-October
91 Subscribers

Construction Update 8-16 to 8-29

Areas referenced below can be located on this map
Work completed 8/16/2020 through 8/22/2020:
  • Completed splicing in Bruin PON
  • Continue splicing in Joslin PON
  • Continued restoration activities
  • Began home drops in Bruin PON
  • Installed 21 home drops in Boyce, Sugarloaf, Long Lake, Wild Goose and Bruin PONs (totals to date: 692 drops – 93 in Werkner PON, 70 in Island Lake PON, 87 in Central Office PON, 130 in Boyce PON, 120 in Sugarloaf PON, 43 in Guinan PON, 83 in Long Lake PON, 51 in Wild Goose PON and 15 in Bruin PON).
  • Spliced 20 home drops in Boyce, Sugarloaf, and Wild Goose PONs (totals to date: 647 spliced – 93 in Werkner PON, 67 in Island Lake PON, 87 in Central Office PON, 128 in Boyce PON, 111 in Sugarloaf PON, 42 in Guinan PON, 81 in Long Lake PON, and 38 in Wild Goose PON).
  • Completed 12 new home installations in Werkner, Central Office, Boyce, Sugarloaf, Guinan, Long Lake and Wild Goose PONs (totals to date: 571 with broadband – 92 in Werkner PON, 67 in Island Lake PON, 84 in Central Office PON, 122 in Boyce PON, 103 in Sugarloaf PON, 38 in Guinan PON, 63 in Long Lake PON, and 2 in Wild Goose PON).
Work to be completed 8/23/2020 through 8/29/2020:
  • Continue splicing in Joslin PON
  • Continue to install home drops in Bruin PON
  • Continue home drop splicing in Sugarloaf and Wild Goose PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf,  Guinan, Long Lake and Wild Goose PONs
  • Continue restoration activities
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (93) complete
Home Installations 99% (92) complete
93 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (70) complete
Home Installations 96% (67) complete
70 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 94% (84) complete
89 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (130) complete
Home Installations 93% (122) complete
131 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (120) complete
Home Installations 86% (103) complete
120 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 88% (38) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (83) complete
Home Installations 76% (63) complete
83 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (51) complete
Home Installations 4% (2) complete
Note:  Home installations were scheduled to begin in early September and have already begun.
51 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 27% (15) complete
Home Installations begin late September
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin late August
Home Installations begin early October
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-September
Home Installations begin mid-October
91 Subscribers

Construction Update 8-9 to 8-22

Areas referenced below can be located on this map
Work completed 8/9/2020 through 8/15/2020:
  • Spliced in Bruin and Joslin PONs
  • Continued restoration activities
  • Installed 12 home drops in Island Lake and Wild Goose PONs (totals to date: 671 drops – 93 in Werkner PON, 70 in Island Lake PON, 87 in Central Office PON, 128 in Boyce PON, 119 in Sugarloaf PON, 43 in Guinan PON, 82 in Long Lake PON and 49 in Wild Goose PON).
  • Spliced 21 home drops in Wild Goose PON (totals to date: 627 spliced – 93 in Werkner PON, 67 in Island Lake PON, 87 in Central Office PON, 127 in Boyce PON, 107 in Sugarloaf PON, 42 in Guinan PON, 81 in Long Lake PON, and 23 in Wild Goose PON).
  • Completed 14 new home installations in Werkner, Island Lake, Sugarloaf, and Long Lake PONs (totals to date: 559 with broadband – 91 in Werkner PON, 67 in Island Lake PON, 83 in Central Office PON, 120 in Boyce PON, 101 in Sugarloaf PON, 37 in Guinan PON and 60 in Long Lake PON).
Work to be completed 8/16/2020 through 8/22/2020:
  • Continue splicing in Bruin and Joslin PONs
  • Begin to install home drops in Bruin PON
  • Continue home drop splicing in Sugarloaf and Wild Goose PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf,  Guinan and Long Lake PONs
  • Continue restoration activities
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (93) complete
Home Installations 98% (91) complete
93 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (70) complete
Home Installations 96% (67) complete
70 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 93% (83) complete
89 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (128) complete
Home Installations 92% (120) complete
131 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (119) complete
Home Installations 85% (101) complete
119 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 86% (37) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (82) complete
Home Installations 73% (60) complete
82 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (49) complete
Home Installations begin early September
49 Subscribers 

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-August
Home Installations begin late September
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin late August
Home Installations begin early October
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-September
Home Installations begin mid-October
91 Subscribers