Construction Update 2-10 to 2-23

Areas referenced below can be located on this map

Work completed 2/10 through 2/16:
  • Bored 528 feet on Werkner Road (Werkner PON)
  • Bored 1,367 feet on N Territorial (Island Lake PON)
  • Bored 385 feet on N Territorial (Central Office PON)
  • Note: No boring on February 12 and 13 due to weather
  • 561 total sign-ups for Broadband service
  • Held in-person Broadband Implementation Committee meeting on February 11
  • Received approval for Department of Natural Resources easements in Pinckney Recreation Area and Waterloo Recreation Area.
Work to be completed 2/17 through 2/23:
  • 2 to 4 crews on-site
  • Continue boring on Werkner Road and N Territorial Road
  • Begin discussions with Stantec (B2B trail contractor) regarding the pedestrian tunnel that will be crossing the Lyndon Township fiber along M-52 near Green Lake

Construction Update 2-3 to 2-16

Areas referenced below can be located on this map

Work completed 2/3 through 2/9:
  • Bored 1,097 feet on Island Lake Road plus set 6 peds and 2 flowerpots
  • Bored 815 feet on Werkner Road plus set 4 peds and 1 tie-in
  • Bored 227 feet on South Drive
  • Bored 1,644 feet on N Territorial
  • 525 total sign-ups (170 Basic, 180 Ultra, 171 G, 4 undecided, 120 phone)
Work to be completed 2/10 through 2/16:
  • 4 crews on-site
  • Finish boring on Island Lake Road
  • Continue boring on Werkner Road and N Territorial Road

Construction Update January 20-February 9

Areas referenced below can be located on this map

Work completed 1/20 through 1/26:
  • Bored 1,008 feet on Island Lake Road (Island Lake PON)
  • Bored 245 feet on Werkner Road (Werkner PON)
  • Submitted WCRC permit application for Waterloo Road (the last one!)
  • Ordered remaining fiber
Due to the weather, no boring was completed between January 27 and February 1.
Work to be completed 2/3 through 2/9:
  • Continue boring on Island Lake Road (Island Lake PON) with 3 crews
  • Last of the fiber to be delivered to Canton warehouse
  • Submit 4 Livingston County Road Commission permit applications (Note: These permit applications will need to be signed by both Lyndon Township and H&M.)
    • Bowdish Road – Jaycox to Worden Road
    • Joslin Lake Road – county line to Barnum Road
    • Barnum Road – Hadley Road to Joslin Lake Road
    • Hadley Road – county line to Barnum Road

Construction Update January 13-26

Areas referenced below can be located on this map

Work completed 1/13 through 1/19:
  • Continued boring on Island Lake Road (Island Lake PON)
  • Continued boring on Werkner Road (Werkner PON)
  • Found a residential location in central Lyndon Township for equipment holding
  • Received 24 WCRC permits for 23 roads
    • Beeman Road
    • Westborne Court
    • Osius Road
    • Oakridge Road
    • Boyce Road
    • Bowdish Road
    • Bush Road
    • Clark Lake Road
    • Lingane Road
    • Gaddis Road
    • Hadley Road
    • Joslin Lake Road (2 permits)
    • Guinan Road
    • Goodband Road
    • Fourth Street
    • First Street
    • Cassidy Road
    • Bartell Road
    • Leeke Road
    • North Lake Road
    • Second Street
    • Watt Road
    • Wild Goose Lake Road
  • Received 3 drain use permits from Washtenaw County Water Resources Commission (waiting for updated version with corrected expiration date)
  • MEC posted the January construction update
  • Residents who have not signed up for service yet received the January postcard
Work to be completed 1/20 through 1/26:
  • Continue boring on Island Lake Road (Island Lake PON)
  • Continue boring on Werkner Road (Werkner PON)
  • Submit WCRC permit application for Waterloo Road (3 WCRC permits remain to be approved – Waterloo Road, Joslin Lake Drive and Roepke Road)

Note:  Due to weather conditions and equipment issues, little boring progress has been made in the past two weeks.

Construction Updates December 12 – January 11

Areas referenced below can be located on this map
Work completed 12/16 through 1/4:
  • Staked 4,162 feet on Boyce Drive (Boyce PON)
  • Three drill crews on-site
  • Bored 1,952 feet on Island Lake Road (Island Lake PON)
  • Completed boring 3,469 feet on Ellsworth Lake Road (Ellsworth PON)
  • 3 pedestals and 2 handholes placed in Werkner PON
Work to be completed 1/7 through 1/11:
  • Four drill crews on-site
  • Continue boring on Island Lake Road (Island Lake PON)
  • Continue boring on Werkner Road (Werkner PON)
  • No flagging and minimal staking is expected for the week

 

Construction Updates December 15 – January 2

Work completed 12/9 through 12/15:
  • Bored 208 feet at Lyndon Township Hall (Central Office PON)
  • Received first pedestal order and installed first pedestals on Greystone Drive (Central Office PON)
  • Bored 2,184 feet on Ellsworth Lake Road (Ellsworth PON)
  • Attended December 11 pre-construction meeting with Washtenaw County Road Commission, H&M and Lyndon Township
Work to be completed 12/16 through 12/22:
  • Continue staking on private roads
  • Three drill crews on-site
  • Begin boring on Island Lake Road (Island Lake PON)
  • Continue boring on Ellsworth Lake Road (Ellsworth PON)
Work to be completed 12/23 through 1/2/2019:
  • No field work planned
  • Work to resume on January 3, 2019

Construction updates December 2-15

Areas referenced below can be located on this map
Work completed 12/2 through 12/8:
  • Staked 1,645 feet on Hidden Lake Drive (Wild Goose PON)
  • Staked 491 feet on Plourde Circle (Wild Goose PON)
  • Bored 2,100 feet on Greystone Drive (Central Office PON)
  • Signed and received permits from WCRC for first 12 roads
    • Werkner Road
    • Island Lake Road
    • N Territorial Road
    • Mester Road
    • Waterloo Road (Werkner PON only)
    • Island Lake Drive
    • Lindley Road
    • Rex Road
    • Stofer Road
    • Roe Road
    • Jaycox Road
    • Farnsworth Road
  • Met with snake expert for introductions and prioritized work activities
  • Placed first fiber order
  • Placed first pedestal order
  • Validated process for Notice to Proceed by road for wetland areas and Tier 1 snake habitat
Work to be completed 12/9 through 12/15:
  • Continue staking on private roads
  • Two drill crews on-site
  • Bore remaining 100 feet on Stoney Ridge Road (Werkner PON)
  • Complete boring on Greystone Drive (Central Office PON) and place first pedestals
  • Begin boring on Ellsworth Lake Road (Ellsworth PON)
  • Begin boring on Werkner Road (Werkner PON)
  • Begin boring on Island Lake Road (Island Lake PON)
  • Attend pre-construction meeting with Washtenaw County Road Commission, H&M and Lyndon Township
  • Begin snake field work
  • Continue to flag wetlands ahead of boring activities
  • Receive first pedestal order