This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact at:  Oversight@lyndonbroadband.org.  

Lyndon Township Completes Broadband Project

QUICK LINKS

MEC CONTACT INFORMATION

Project Updates

Construction Update 4-21 to 5-4

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 4/21 through 5/4: 4 crews on-site Bored 724 feet (Central Office PON) and 3,108 feet (Werkner PON) on Waterloo Road Bored 1,000 feet (Central Office PON) and 584 feet (Island Lake PON) on N Territorial Road Bored 1,360 feet on Mester […]

Construction Update 4-14 to 4-27

Work completed 4/14 through 4/20: 4 to 5 crews on-site Bored 1,336 feet (Werkner PON) and 132 feet (Island Lake PON) on Werkner Road Bored 1,355 feet on Waterloo Road (Werkner PON) Bored 192 feet on Wildflower Ridge (Werkner PON) Bored 132 feet on N Territorial Road (Island Lake PON) Bored 66 feet on Island […]

Construction Update 4-7 to 4-20

Work completed 4/7 through 4/13: 2 to 3 crews on-site Frost laws lifted on April 8 Bored 1,681 feet on Werkner Road between Wildflower Ridge and Waterloo Road (Werkner PON) Installed 3 pedestals on Werkner Road Worked on road crossings and tying in lines for completed borings Residents who have still not signed up received […]

MEC April Construction Update and March 27, 2019 Drop Presentation Slides

Happy Friday Lyndon Township! At our March MEC Meet & Greet, we met with about 70 Lyndon Township residents and offered a presentation about the Drop Installation Process. We wanted to share two key takeaways from that program: We do not contact people before beginning work on your property, unless you requested that during the […]