This site is no longer Active – Please Visit  https://lyndontownshipmi.gov/broadband/  for Current Information 


This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact at:  Oversight@lyndonbroadband.org.  

Lyndon Township Completes Broadband Project

QUICK LINKS

MEC CONTACT INFORMATION

Project Updates

Construction update 5-12 to 5-25

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 5/12 through 5/18: 4 to 6 crews on-site Bored 570 feet on Werkner Road (Werkner PON) Bored 990 feet on Mester Road (Werkner PON) Bored 542 feet on Waterloo Road (Werkner PON) Bored 2,108 feet on Boyce Road (Boyce PON) Installed […]

MEC – May Construction Update

There’s light at the end of the tunnel, literally, as we prepare to bring fiber internet to life at Lyndon Township Hall. In this week’s construction update, Township officials announced that the cabinet and vault were installed last week, and they anticipate that service will be active for next week’s open house. Your MEC Internet […]

Construction update 5-5 to 5-18

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 5/5 through 5/11: 4 crews on-site Bored 290 feet on Werkner Road (Werkner PON) Bored 812 feet on Mester Road (Werkner PON) Installed 15 pedestals in Werkner PON Completed boring along mainline connecting the southeast corner of Lyndon Township to Township […]

Please Read – Drop Installation Process – MISS DIG

The following information will help to better understand the home installation (Drop) process.   MEC (Midwest Energy and Communication) will be doing this work.  Pay particular attention to MISS DIG information. The word Drop,  refers to the the process of bringing the fiber optic cable from the road and attaching it to your home.   As a […]