Work completed 12/9 through 12/15:
- Bored 208 feet at Lyndon Township Hall (Central Office PON)
- Received first pedestal order and installed first pedestals on Greystone Drive (Central Office PON)
- Bored 2,184 feet on Ellsworth Lake Road (Ellsworth PON)
- Attended December 11 pre-construction meeting with Washtenaw County Road Commission, H&M and Lyndon Township
Work to be completed 12/16 through 12/22:
- Continue staking on private roads
- Three drill crews on-site
- Begin boring on Island Lake Road (Island Lake PON)
- Continue boring on Ellsworth Lake Road (Ellsworth PON)
Work to be completed 12/23 through 1/2/2019:
- No field work planned
- Work to resume on January 3, 2019