Construction Updates December 15 – January 2

Work completed 12/9 through 12/15:
  • Bored 208 feet at Lyndon Township Hall (Central Office PON)
  • Received first pedestal order and installed first pedestals on Greystone Drive (Central Office PON)
  • Bored 2,184 feet on Ellsworth Lake Road (Ellsworth PON)
  • Attended December 11 pre-construction meeting with Washtenaw County Road Commission, H&M and Lyndon Township
Work to be completed 12/16 through 12/22:
  • Continue staking on private roads
  • Three drill crews on-site
  • Begin boring on Island Lake Road (Island Lake PON)
  • Continue boring on Ellsworth Lake Road (Ellsworth PON)
Work to be completed 12/23 through 1/2/2019:
  • No field work planned
  • Work to resume on January 3, 2019