Areas referenced below can be located on this map
Work completed 2/10 through 2/16:
- Bored 528 feet on Werkner Road (Werkner PON)
- Bored 1,367 feet on N Territorial (Island Lake PON)
- Bored 385 feet on N Territorial (Central Office PON)
- Note: No boring on February 12 and 13 due to weather
- 561 total sign-ups for Broadband service
- Held in-person Broadband Implementation Committee meeting on February 11
- Received approval for Department of Natural Resources easements in Pinckney Recreation Area and Waterloo Recreation Area.
Work to be completed 2/17 through 2/23:
- 2 to 4 crews on-site
- Continue boring on Werkner Road and N Territorial Road
- Begin discussions with Stantec (B2B trail contractor) regarding the pedestrian tunnel that will be crossing the Lyndon Township fiber along M-52 near Green Lake