This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township, If you are looking for information that you do not find here or would like to ask a question, please contact at: Oversight@lyndonbroadband.org.
Project Updates
Connections from Main Line to Homes
As you know, there are many stages to take the project to conclusion. At each stage we have hired highly qualified firms to carry out the work. This includes Consulting, Engineering, Outside Plant Construction and ISP (Internet Service Provider) We are currently in the process of selecting a firm to install the connections to our […]
Construction Updates December 12 – January 11
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 12/16 through 1/4: Staked 4,162 feet on Boyce Drive (Boyce PON) Three drill crews on-site Bored 1,952 feet on Island Lake Road (Island Lake PON) Completed boring 3,469 feet on Ellsworth Lake Road (Ellsworth PON) 3 pedestals and 2 handholes placed […]
Construction Updates December 15 – January 2
Work completed 12/9 through 12/15: Bored 208 feet at Lyndon Township Hall (Central Office PON) Received first pedestal order and installed first pedestals on Greystone Drive (Central Office PON) Bored 2,184 feet on Ellsworth Lake Road (Ellsworth PON) Attended December 11 pre-construction meeting with Washtenaw County Road Commission, H&M and Lyndon Township Work to be […]
Construction updates December 2-15
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 12/2 through 12/8: Staked 1,645 feet on Hidden Lake Drive (Wild Goose PON) Staked 491 feet on Plourde Circle (Wild Goose PON) Bored 2,100 feet on Greystone Drive (Central Office PON) Signed and received permits from WCRC for first 12 roads […]
Monthly Construction Updates
Midwest Energy and Communications (MEC), our Internet Service Provider, will begin posting monthly construction updates on their website as well as emailing these updates to everyone who has subscribed to the broadband service. The first of these updates is included below. We will post these updates here as well and continue to post other information […]
Middle Mile Work Begins on M-52
Work has begun on M-52 to bring Middle Mile Fiber to Lyndon Township. Middle mile fiber is that section of fiber that connects a network (Lyndon) to the greater world of the internet. Midwest Energy and Communications (MEC), the Internet Service Provider for Lyndon Township is overseeing this work which is the result of a creative […]
Partnership with Chelsea School District moves Lyndon project Forward
The Chelsea School District, Midwest Energy and Communications and Lyndon Township have formed a creative and mutually beneficial partnership that will help move the Lyndon Broadband Project forward. Eead more about the partnership. Chelsea School District partners with Midwest Energy & Communications to bring broadband to Lyndon Township
Construction Update November 30 2018
Staking completed: Central Office zone (Greystone Drive), Long Lake zone (Chestnut Lane, Hickory Lane, Stonehill Drive, Bauer Court), Sugarloaf zone (Sugarloaf Lake Road (partial), Cedar Drive), Ellsworth zone (Ellsworth Lake Road (partial), Roepke Court, Medina Drive) 776 feet bored and conduit placed in ground on Stoney Ridge Road (Werkner Zone) 30 reels of duct received […]
Additional Drilling to begin week of November 12
Beginning the week of November 12, Henkels and McCoy will begin construction on the private roads that have been staked in the Werkner Zone (Stoney Ridge Road) and Island Lake Zone (Beede Drive, South Drive). A map of the zones in the township can be found at: Lyndon Township Zone Map It is important to be […]
Drilling to begin on Broadband Project
On Monday, November 12, drilling will begin along M-52 to bring the main line fiber to Lyndon Township. The drilling will take place along a one mile stretch south of the roundabout at Werkner Road. The fiber will enter Lyndon Township on Werkner Road just east of M-52. Later this month drilling will commence from […]