Construction Update 12-6 to 12-19

Work completed 12/6/2020 through 12/12/2020:
  • Drops complete (Final Totals: 906 drops – 96 in Werkner PON, 76 in Island Lake PON, 86 in Central Office PON, 128 in Boyce PON, 123 in Sugarloaf PON, 43 in Guinan PON, 85 in Long Lake PON, 49 in Wild Goose PON, 55 in Bruin PON, 66 in Joslin PON and 99 in Ellsworth PON).
  • Splices complete (Final Totals: 906 splices – 96 in Werkner PON, 76 in Island Lake PON, 86 in Central Office PON, 128 in Boyce PON, 123 in Sugarloaf PON, 43 in Guinan PON, 85 in Long Lake PON, 49 in Wild Goose PON, 55 in Bruin PON, 66 in Joslin PON and 99 in Ellsworth PON).
  • Completed 10 new home installations in Island Lake, Central Office, Wild Goose, Long Lake, Bruin, and Ellsworth PONs (totals to date: 904 with broadband – 96 in Werkner PON, 76 in Island Lake PON, 86 in Central Office PON, 128 in Boyce PON, 122 in Sugarloaf PON, 43 in Guinan PON, 85 in Long Lake PON, 49 in Wild Goose PON, 55 in Bruin PON, 65 in Joslin PON, and 99 in Ellsworth PON).
Work to be completed 12/13/2020 through 12/19/2020:
  • Complete home installations in Sugarloaf and Joslin PONs
  • Complete Lyndon Township Implementation Project effective December 19, 2020
  • Transition remaining Implementation Committee responsibilities to Oversight Committee members
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (96) complete
Home Installations 100% (96) complete
96 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (76) complete
Home Installations 100% (76) complete
76 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (86) complete
Home Installations 100% (86) complete
86 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (128) complete
Home Installations 100% (128) complete
128 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (123) complete
Home Installations 99% (122) complete
123 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 100% (43) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (85) complete
Home Installations 100% (85) complete
85 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (49) complete
Home Installations 100% (49) complete
49 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (55) complete
Home Installations 100% (55) complete
55 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (66) complete
Home Installations 98% (65) complete
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (99) complete
Home Installations 100% (99) complete
99 Subscribers

Posted in Uncategorized, Updates.