Construction Update 11-29 to12-12

Areas referenced below can be located on this map

Work completed 11/29/2020 through 12/5/2020:
  • Installed 1 home drop in Bruin PON (totals to date: 906 drops – 96 in Werkner PON, 76 in Island Lake PON, 86 in Central Office PON, 128 in Boyce PON, 123 in Sugarloaf PON, 43 in Guinan PON, 85 in Long Lake PON, 49 in Wild Goose PON, 55 in Bruin PON, 66 in Joslin PON and 99 in Ellsworth PON).
  • Spliced 5 home drops in Long Lake, Bruin, Joslin and Ellsworth PONs (totals to date: 906 spliced – 96 in Werkner PON, 76 in Island Lake PON, 86 in Central Office PON, 128 in Boyce PON, 123 in Sugarloaf PON, 43 in Guinan PON, 85 in Long Lake PON, 49 in Wild Goose PON, 55 in Bruin PON, 66 in Joslin PON and 99 in Ellsworth PON).
  • Completed 5 new home installations in Boyce, Long Lake, and Ellsworth PONs (totals to date: 894 with broadband – 96 in Werkner PON, 75 in Island Lake PON, 85 in Central Office PON, 128 in Boyce PON, 122 in Sugarloaf PON, 43 in Guinan PON, 84 in Long Lake PON, 48 in Wild Goose PON, 54 in Bruin PON, 65 in Joslin PON, and 94 in Ellsworth PON).
Work to be completed 12/6/2020 through 12/12/2020:
  • Continue home installations in Island Lake, Central Office, Long Lake, Wild Goose, Bruin, and Ellsworth PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (96) complete
Home Installations 100% (96) complete
96 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (76) complete
Home Installations 99% (75) complete
76 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (86) complete
Home Installations 99% (85) complete
86 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (128) complete
Home Installations 100% (128) complete
128 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (123) complete
Home Installations 99% (122) complete
123 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 100% (43) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (85) complete
Home Installations 99% (84) complete
85 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (49) complete
Home Installations 98% (48) complete
49 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (55) complete
Home Installations 98% (54) complete
55 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (66) complete
Home Installations 98% (65) complete
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (99) complete
Home Installations 95% (94) complete
99 Subscribers

Posted in Uncategorized, Updates.