This site is no longer Active – Please Visit  https://lyndontownshipmi.gov/broadband/  for Current Information 


This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township,  If you are looking for information that you do not find here or would like to ask a question, please contact at:  Oversight@lyndonbroadband.org.  

Lyndon Township Completes Broadband Project

QUICK LINKS

MEC CONTACT INFORMATION

Project Updates

Construction Update 10-13 to 10-26

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 10/13 through 10/19: 9 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 1,063 feet on M-52 (Central Office PON) Bored 264 feet on Leeke Road (Boyce PON) Bored 1,479 feet on Roe Road (Boyce PON) Bored […]

Drop Information

Drop is the term used to describe the process of bringing the fiber optic cable from the main line fiber at the road and connecting it to an enclosure on your residence. Here is information about the process and sequence of events that will occur. MEC’s Underground Contractor (drop installer) will call in a request […]

Construction Update 10-6 to 10-19

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 10/6 through 10/12: 9 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 1,534 feet on M-52 (Central Office PON) Bored 911 feet on Leeke Road (Boyce PON) Bored 773 feet on Cassidy Road (Boyce PON) Bored […]

Construction Update 9-25 to 10-12

Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 9/29 through 10/5: 8 to 9 bore crews on-site plus one fiber pulling crew and one splicing crew Bored 774 feet on M-52 (Central Office PON) Bored 800 feet on North Territorial Road (Central Office PON) Bored 1,158 feet on Roepke […]