- Installed 2 home drops in Ellsworth PONs (totals to date: 908 drops – 96 in Werkner PON, 76 in Island Lake PON, 85 in Central Office PON, 128 in Boyce PON, 123 in Sugarloaf PON, 42 in Guinan PON, 84 in Long Lake PON, 47 in Wild Goose PON, 54 in Bruin PON, 75 in Joslin PON and 98 in Ellsworth PON).
- Spliced 4 home drops in Island Lake and Ellsworth PONs (totals to date: 904 spliced – 96 in Werkner PON, 76 in Island Lake PON, 85 in Central Office PON, 128 in Boyce PON, 122 in Sugarloaf PON, 42 in Guinan PON, 84 in Long Lake PON, 47 in Wild Goose PON, 54 in Bruin PON, 74 in Joslin PON and 95 in Ellsworth PON).
- Completed 28 new home installations in Bruin, Joslin and Ellsworth PONs (totals to date: 833 with broadband – 96 in Werkner PON, 75 in Island Lake PON, 85 in Central Office PON, 127 in Boyce PON, 122 in Sugarloaf PON, 42 in Guinan PON, 83 in Long Lake PON, 46 in Wild Goose PON, 54 in Bruin PON, 61 in Joslin PON, and 42 in Ellsworth PON).
- Continue home installations in Joslin and Ellsworth PONs
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (96) complete
Home Installations 100% (96) complete
96 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (76) complete
Home Installations 99% (75) complete
76 Subscribers
Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (85) complete
Home Installations 100% (85) complete
85 Subscribers
Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (128) complete
Home Installations 99% (127) complete
128 Subscribers
Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (123) complete
Home Installations 99% (122) complete
123 Subscribers
Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (42) complete
Home Installations 100% (42) complete
42 Subscribers
Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (84) complete
Home Installations 99% (83) complete
84 Subscribers
Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (47) complete
Home Installations 98% (46) complete
47 Subscribers
Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (54) complete
Home Installations 100% (54) complete
54 Subscribers
Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (75) complete
Home Installations 81% (61) complete
75 Subscribers
Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (98) complete
Home Installations 43% (42) complete
98 Subscribers