Work completed 1/7 through 1/11:
  • Continued boring on Island Lake Road (Island Lake PON)
  • Continued boring on Werkner Road (Werkner PON)
Work to be completed 1/7 through 1/11:
  • Three to four drill crews on-site
  • Continue boring on Island Lake Road (Island Lake PON)
  • Continue boring on Werkner Road (Werkner PON)
  • Place another fiber order
  • Find another holding location for construction equipment (expected to be at a Lyndon Township property owner as opposed to downtown Chelsea)
  • Identify a water source (not Chelsea) for construction crews
  • Submit WCRC permit for Hadley Road